A message from MoDOT
August 10th update
The Missouri Department of Transportation would like to let you know that work to repair the driving surface on the Phelps County Route BB bridge over BNSF Railway in Rolla is scheduled to begin Monday, Aug. 17.
The bridge will remain open throughout construction, with one lane of traffic open in each direction. Motorists should expect delays.
For motorists' safety while work is occurring overhead, intermittent closures of Oak Street and Olive Street beneath the bridge will be necessary when crews are working in the immediate area. These closures will not be in place for the duration of construction, and traffic will be directed to use surrounding local roadways when closures are in effect.
The project is expected to continue through November 2026, weather permitting, subject to change.
______________________________
August 6th update
I have a long-anticipated update on the two bridges currently being rehabilitated by Concrete Strategies, LLC as part of a MoDOT project to rehabilitate six bridges over I-44 in Phelps and Pulaski Counties. The Route 28, Route D and Sugar Tree Road bridges over I-44 have been completed, but Route J and Kingshighway are under construction with Route E still to go.
- Phelps County Route J, 10 miles southwest of Doolittle (Exit 169).
- Work is wrapping up and the contractor could open the bridge as early as next Friday, Aug. 14.
- Phelps County Business U.S. 44/Missouri Route 72/Kingshighway in Rolla.
- Extensive deterioration – more than expected – was discovered when the contractor began rehabilitating the bridge deck. This required additional work and time to ensure a quality, long-lasting product.
- Crews are moving to the second half of the project, and barring the discovery of more unexpected deterioration, they plan to open the westbound lanes to traffic in mid-October.
- Eastbound lanes remain open
- Route E, at Exit 185 in Rolla will begin the evening of Aug. 17. Crews will remove the sidewalk adjacent to the northbound lanes under single-lane closures with flaggers. Work will be done at night and is expected to continue through early October.